Bong - And Here Is The News - Big Ben to Be Silenced UPDATE

Since ThisWeekinFM reported this story on Monday Aug 14, MPs, concerned the Bell & Chimes would be silenced for too long, have intervened to consider if the period of silence can be shortened from the proposed four years.

One reason for silencing the Bell & Chimes is the risk to the hearing of those working on the project.

 

One of the world's most interesting maintenance jobs will get underway next week (Aug 21) as London and Parliaments Big Ben is silenced for four years and the bell's home, the Elizabeth Tower  is refurbished.

Crowds are being encouraged to Parliament Square for noon on Monday 21 to celebrate BB's last bong and as the hourly chimes are silenced so the Great Clock can be worked on. The chimes were stopped in 1983 and 2007 again for maintenance. Big Ben will still bong on New Year's Eve.

Specialist teams carry out regular maintenance and adjustments to the Great Clock. However, problems have been identified with the clock hands, mechanism and pendulum, which need to be dealt with immediately to ensure that the clock can continue to work properly. Surveys are still being carried out to identify the extent of the works required to the Tower itself but areas of concern have been identified, including cracks in masonry, leaks, erosion and severe rusting of metalwork.

There is a risk that if not addressed as a matter of urgency, the clock may fail or fabric problems may become acute.

 

Fire Regs and H&S

One reason the Tower works have been scheduled now rather than when the whole of the Parliament buildings are renovated, is the Tower needs to be brought in line with fire prevention guidance and health and safety measures for staff and visitors need to be improved immediately.

In order to provide a better means of emergency evacuation, and to improve accessibility for a wider range of people, a lift will be installed within the existing ventilation shaft of the Tower.

 

1983-85

The last significant conservation work was completed in 1983-85. This involved the cleaning and repair of the stone, painting and gilding works and repairs to the cast iron roof. The structure was stabilised in 1995/96 as a result of works carried out to the Jubilee Line. Parts of the clock mechanism were serviced in 2007 but other areas haven’t been overhauled in over 25 years.

 

The 2017-21 project includes:

  • Work to prevent the clock mechanism from failing, as it is currently in a chronic state.
  • Addressing urgent problems caused by decay to the fabric of the building, both internally and externally.
  • Health & safety and fire safety improvements, including installation of a lift.
  • Enhanced energy efficiency through modern lighting of the tower face and other measures.

Overall the project’s aim is to repair and conserve the Tower, upgrade facilities as necessary and to ensure its integrity for future generations. Exterior scaffolding will be required - with the clock face visible for as long as is practicable. One working clock face will be visible throughout the works, the hands of  which will be driven by an electric motor. However, the clock mechanism itself will be stopped at times during the works in order to repair the hands, bearings, gears and drive mechanism.

 

 

Contracts

Public sector procurement is governed by UK regulations that implement the EU procurement directives the works will therefore be let through a contract that has been tendered via the EU procurement OJEU process. The clock mechanism repairs will be carried out by the internal team where possible. Costs are expected to be £29 million (inclusive of VAT). The Medium Term Investment Plan of the Parliamentary Estates will stump-up the cash.

 

Sitting

The Ayrton light will still shine to show the Houses are sitting - but it will be a substitute whilst the original is being repaired.

 

Why install a lift in the Tower?

At present there is only a single spiral staircase with 334 steps. Emergency evacuation from the Tower is currently carried out using a complex abseiling rig. To improve safety and to help reduce the time it takes to evacuate an injured person from the Tower in the event of an emergency, a lift will be installed in one of the existing ventilation shafts. The lift will also provide improved access (though not full access due to constraints of the space) for some disabled people who are currently unable to use the stairs and will improve access to the clock for maintenance purposes. It will have no impact on the external appearance.

 

Restoration and Renewal Programme

The Parliament Restoration and Renewal Programme is unlikely to start until the early 2020s.

Picture Parliamentary Copyright: The Elizabeth Tower - home to the Great Clock, the chimes and of course, Big Ben 

Article written by Brian Shillibeer

Share



Related Articles

Lousy London Lifts Listed

London Firefighters attend 13 non urgent lift call outs every single day - day in day out. That's nearly 5,000 incidents a year in the capital alone. And this only...

 Read Full Article
Lousy London Lifts Listed

London Firefighters attend 13 non urgent lift call outs every single day - day in day out. That's nearly 5,000 incidents a year in the capital alone. And this only...

 Read Full Article
Panic on the Streets of London - 21 Firefighters Called to Blaze

Fire on Oxford Street picture with thanks to Twitter Mo Firefighters tackled a fire in a building undergoing refurbishment on London’s famous shopping...

 Read Full Article
Cladding Fire Fears - Unit Closed and Patients Moved

Oxford University Hospitals NHS Foundation Trust has received a report on fire safety in the Trauma Unit at the John Radcliffe Hospital. An extraordinary Board Meeting...

 Read Full Article
Game, Set and Match as Landlords Get Record Fine

Friday may 26 saw crews called to fire in hedgerow at Wimbledon Tennis Club Four fire engines and 21 firefighters and officers went to a practice court area of the All...

 Read Full Article
Judge Dread - Nightmare 45 Minutes in Lift Delays Sentencing

A man was sentenced on Thursday 18 at the Old Bailey for manslaughter. The verdict was delayed on Wednesday as his judge was stuck in a lift! The convict now be...

 Read Full Article
Thumbs Down for Thumb Loss

PD Lift Services Limited has been fined £36,000 after a worker lost his thumb while working on passenger lifts. Westminster Magistrates Court heard how the...

 Read Full Article
Explosion Kills Man - Fire Closes Hotel

Police, the London Ambulance Service, the Fire Brigade and eventually the London Air Ambulance were called to an explosion at a building site on Thursday 16 in...

 Read Full Article
Fire in the Hold as Galaxy Sevens Don't Go Back

Samsung has stated that only about 60 per cent of owners have returned their Note 7 device for a replacement despite them being a serious fire risk - including on a...

 Read Full Article
Brighton Rocked - Sticky Situation as i360 Gets Stuck

You couldn't have written it - well ThisWeekinFM could - the brand new British Airways' observation tower (which opened to the public on August 4 on Brighton...

 Read Full Article